A closeboard fence is built on site from posts, arris rails and overlapping feather-edge boards. The overlap is what most lists get wrong.

Updated Based on manufacturer guidance, sources below

The short answer

With 100mm feather-edge boards overlapping by 25mm, each board covers 75mm, so you need about 13.3 boards per metre plus 10%. A 10m fence, 1.8m high, needs 147 boards, 7 posts, 18 arris rails, 6 gravel boards and about 440 fixings.

The formula

  • Bays = fence length / 1.83m, rounded up. Posts = bays + 1
  • Arris rails = bays x 3 for fences over 1.2m high (2 for lower fences)
  • Feather-edge boards = fence length / 0.075m x 1.1
  • Fixings = boards x rails (one per board at each rail)

Worked example

A 10m closeboard fence, 1.8m high:

  • Bays: 10 / 1.83 = 5.5, so 6 bays and 7 posts (75 x 75mm x 2.4m: 1.8m + 600mm in the ground)
  • Arris rails: 6 x 3 = 18
  • Boards: 10 / 0.075 = 133, plus 10% = 147
  • Fixings: 147 x 3 = 441, so 3 packs of 200
  • Gravel boards: 6. Postcrete: 7 bags

Work it out for your job

Change the measurements and the quantities update straight away.

Bays (1.83m)
6
Feather-edge boards
147 (13.3 per metre + 10%)
Board fixings
~441 (1 per board per rail)

Your list

  • 7Posts 75 x 75mm x 2.4m
  • 6Gravel boards 150mm x 1.83m
  • 18Arris rails 3.0m (3 per bay)
  • 147Feather-edge boards 100mm x 1.65m
  • 7Postcrete 20kg
  • 3Exterior screws 4 x 40mm, packs of 200
  • 1Screws 5 x 60mm for rails and gravel boards, packs of 200
  • 3Fence stain 2.5L (one side, optional)
Price this closeboard fence

Opens SmartBuild with your measurements filled in. Every item is priced from live supplier feeds, ranked by price.

Materials checklist

  • Fence posts75 x 75mm x 2.4m when height + 600mm is 2.4m or less; otherwise 100 x 100mm x 3m.
  • Arris railsTriangular rails between the posts: 3 per bay over 1.2m high, 2 below.
  • Feather-edge boards100mm boards overlapping 25mm, about 13.3 per metre.
  • Gravel boardsOne per bay at the bottom, so the boards stay off the soil.
  • PostcreteOne bag per 75mm post.
  • Exterior screws or galvanised nailsOne per board at each rail, plus screws for rails and gravel boards.
  • Fence treatment (optional)Pressure-treated timber does not strictly need it. About 6 m² per 2.5L tin on rough-sawn boards, 2 coats.

You'll also need

  • Arris rail brackets (2 per rail) if the posts are not morticed
  • Post caps and a capping rail
  • Spade or post-hole digger, spirit level, string line
  • A spacer cut from a 75mm offcut

Step by step

  1. Set out the lineRun a string line and mark post positions every 1.83m.
  2. Set the postsDig 600mm holes and set each post plumb in Postcrete.
  3. Fit rails and gravel boardsFix the arris rails between the posts and a gravel board at the bottom of each bay.
  4. Fix the boardsFit feather-edge boards with each thick edge overlapping the thin edge of the last board by 25mm, using a spacer to keep the overlap even.
  5. FinishFit post caps and a capping rail if you are using one, then treat the timber if you want a colour.

Tips from the manufacturers

  • Make a spacer from a 75mm offcut so every board overlaps by the same 25mm. Check with a level every few boards.
  • Fix each board once at each rail, near its thick edge, so the fixing misses the board underneath. That lets the timber move without splitting.
  • Feather-edge boards in our list are 1.65m long, which suits a 1.8m fence on a 150mm gravel board. Taller fences need longer boards.
  • Ronseal quotes about 4 to 6 m² per litre per coat for Fence Life Plus on rough-sawn timber, so allow about 6 m² per 2.5L tin for two coats.

Mistakes to avoid

  • Spacing boards at 120mm (wider than the board), which leaves gaps and leaves you about 35% short on boards.
  • Using 2 arris rails on a fence over 1.2m high, which lets the boards bow.
  • Nailing through both overlapping boards, so they split as the timber moves.
  • Building over 2m high (or 1m next to a road) without planning permission.

Frequently asked questions

How many feather-edge boards per metre?

With 100mm boards overlapping by 25mm, about 13.3 per metre. Add 10% for cuts and splits.

How much should feather-edge boards overlap?

About 25mm is typical for 100mm boards, leaving 75mm of each board showing.

How many arris rails do I need?

Three per bay on fences over 1.2m high and two per bay for lower fences. Each 1.83m bay uses one 3m rail cut to length.

What size posts for a closeboard fence?

75 x 75mm posts suit fences up to 1.8m when 600mm goes in the ground. Taller fences need 100 x 100mm posts.

How many nails or screws for feather-edge boards?

One per board at each rail. A 10m, 1.8m fence with 147 boards and 3 rails needs about 440 fixings.

Sources

Quantities are estimates for typical jobs, using the coverage figures above. Products vary, so check the data sheet for the product you buy, and talk to a professional for structural, electrical or gas work. SmartBuild is independent and not affiliated with any of the manufacturers listed.

Get the full priced list

Open SmartBuild with your measurements and see the total from live supplier prices. Free, no sign-up.

Open in SmartBuild